Client
Isambard Kingdom Brunel (IKB) Primary School
Building Use
14 class primary school with an on-site nursery
Procurement Method
Buy
Why buy from PortakabinProject Features
- 14 class primary school with an on-site nursery
- Specialist arts and science areas
- Multi-activity studio
- Library
- Double height modular hall
- Forest school
-
The Requirements
When the UK went into ‘lockdown’ on Monday 23 March, Portakabin had just completed the offsite fit-out of Isambard Kingdom Brunel (IKB) Primary School and it was on the yard of its manufacturing facility in York. The building was ready to despatch with all groundworks and foundations having already been completed on site. With the restrictions brought in almost immediately, the Health and Safety team at Portakabin designed custom operating procedures, in line with Government guidelines, to enable the IKB team to install the building as planned.
-
The Solution
The short term impact of COVID-19 on the productivity of the construction industry could be described as catastrophic. But by limiting the number of operatives on site, the Portakabin team at IKB were able to progress external works, while the challenge of delivering the physical modules to site was finalised. Trades were allocated areas of the site in sequence to ensure social
distancing guidelines were met allowing everyone to continue to operate in a safe working environment.
It was reassuring to see Portakabin was capable of delivering an ‘MMC Solution’ during this challenging time. The team were able to safely manage the risk associated with social distancing on site as well as in its manufacturing facilities to deliver a high quality facility.
A unique promise for your complete peace of mind
Knowing you will meet your targets is a great starting point for any building project
Buckton Fields Primary School
Buckton Fields Primary School
In just four months, 44 temporary buildings were installed to provide high-quality teaching, learning and welfare space for 180 pupils.
In just four months, 44 temporary buildings were installed to provide high-quality teaching, learning and welfare space for 180 pupils.
Project Features
- Radon membrane barrier
- Early year playground with equipment and astroturf
- Air conditioning and access control
- Installation of new soakaway
- Timber-effect vinyl wrap with school logo
- Internal graphics
- Oak-effect vinyl flooring
- New secure line fencing, fire tender road, pedestrian route to entrance and new gates
- Grass area and pathways
Haygrove School
Haygrove School
First of three schools delivered in record-breaking time with spacious classrooms, offices, canteens, science labs and games rooms.
First of three schools delivered in record-breaking time with spacious classrooms, offices, canteens, science labs and games rooms.
Project Features
- Four separate teaching blocks
- Fully fitted science classrooms
- Powered access doors
- Full production kitchen and dining hall
- Science labs
- Games room
- Staff offices and break rooms
Silverdale School
Silverdale School
Three storey extension to existing secondary school building
Three storey extension to existing secondary school building
Project Features
- External terrace/play area for children
- Kiln install for art classrooms
- Platform lift
- Photovoltaic roof and green roof system
- Rendered, bricks and cladding panels to match existing building