Client
Wymondham High Academy
Building Use
Classrooms
Project Duration
12 weeks
Procurement Method
Buy
Why buy from PortakabinProject Features
- Five seminar rooms
- Break-out area
- Administration office
-
The Requirements
Wymondham High in Norfolk is a mixed academy specialising in the arts and sciences. Its sixth form has been recognised as ‘outstanding' by Ofsted and it has been listed as one of the best performing schools in East Anglia. With plans to increase pupil numbers, a dedicated centre was required for the sixth form.
-
The Solution
A single-storey building, designed by architects NPS South East and constructed using a highly sustainable recycled modular building from Portakabin, was craned into position in just one day during the school holidays to minimise disruption to staff and students. It was completed ahead of schedule, reducing the programme from receipt of order to less than three months.
A collaborative approach was taken to the design of the new building, which accommodates five seminar rooms for students studying social sciences, and sixth form facilities, including a break-out area, toilets and administration office. The exterior aesthetics were discussed at workshops with sixth form design students, who were keen to use sustainably-sourced timber and to introduce colour into the project. A cladding solution was developed using natural larch with vertical ‘windows' cut out to reveal the modular steel structure finished in three colours – jade, heritage green and Wedgewood blue.
Portakabin (Refurbished) modular buildings are fitted with new windows, wall linings, partitions, mechanical and electrical services, doors, flooring, and cladding, to create high quality accommodation for a wide variety of education applications. Off-site working is maximised for safer, quieter, cleaner sites and reduced disruption to teaching. The buildings can easily be expanded, reconfigured or removed if teaching requirements change.
The Portakabin team was very helpful, personable and efficient throughout and the modular solution has given us the very best scheme for our available budget.
A unique promise for your complete peace of mind
Knowing you will meet your targets is a great starting point for any building project
Jericho Primary School
Jericho Primary School
Temporary classrooms installed in eight weeks after storm Eowyn hits
Temporary classrooms installed in eight weeks after storm Eowyn hits
Project Features
- Water and waste connections
- External ramp for access
- Air conditioning throughout
- Groundworks / foundations and pathways
Buckton Fields Primary School
Buckton Fields Primary School
In just four months, 44 temporary buildings were installed to provide high-quality teaching, learning and welfare space for 180 pupils.
In just four months, 44 temporary buildings were installed to provide high-quality teaching, learning and welfare space for 180 pupils.
Project Features
- Radon membrane barrier
- Early year playground with equipment and astroturf
- Air conditioning and access control
- Installation of new soakaway
- Timber-effect vinyl wrap with school logo
- Internal graphics
- Oak-effect vinyl flooring
- New secure line fencing, fire tender road, pedestrian route to entrance and new gates
- Grass area and pathways
Haygrove School
Haygrove School
First of three schools delivered in record-breaking time with spacious classrooms, offices, canteens, science labs and games rooms.
First of three schools delivered in record-breaking time with spacious classrooms, offices, canteens, science labs and games rooms.
Project Features
- Four separate teaching blocks
- Fully fitted science classrooms
- Powered access doors
- Full production kitchen and dining hall
- Science labs
- Games room
- Staff offices and break rooms